Steel mezzanine with yellow stair inside a live distribution centre

Industrial & logistics case study

Distribution Centre

Kettering, confidential client

Parogon built a new 35,000 sq ft mezzanine floor inside an operating 200,000 sq ft distribution centre: £2.4m over 16 weeks. The construction zone was sectioned off behind a temporary full-height jumbo stud partition so the client's business carried on, with civils and steel, three goods lifts, new conveyors with compressed air and fire suppression, and new sprinklers, lighting and detection.

Client
Confidential
Location
Kettering
Value
£2.4 million
Construction
16 weeks
Building
200,000 sq ft
Steel framework and racking running the length of the building
Steel and racking, the length of the building.
New mezzanine with yellow stair
The new mezzanine, and the stair up to it.
Operatives carrying panels on the works side of the partition
Panels going in, on the works side of the partition.

Sealed off

A temporary full-height jumbo stud partition kept the operation dust-free.

No shutdown

A floor inside a floor

35,000 sq ft of mezzanine on new civils and steel framework.

35,000 sq ft

Moving goods

Three goods lifts and new distribution conveyors with compressed air and fire suppression.

3 lifts

Life safety

New sprinklers, high and low-level lighting and fire detection.

16 weeks

Warehouse floor with column guards and racking beyond
The finished floor, before the racking went in.

The Result

No shutdown. No dust on the pick faces. Every order went out.

No shutdown

The distribution centre kept operating for all 16 weeks.

No dust on the pick faces

A full-height partition sealed the works from the live floor.

Every order went out

Steel, lifts and conveyors sequenced around daily dispatch.

Industrial & logistics

Need to build without stopping the operation?

Parogon builds inside working warehouses, plants and distribution centres, behind the partitions that keep your business running.

Talk to Parogon