Distribution Centre

Kettering, confidential client

Client
Confidential
Location
Kettering
Value
£2.4 million
Construction
16 weeks
Building
200,000 sq ft

Parogon built a new 35,000 sq ft mezzanine floor inside an operating 200,000 sq ft distribution centre: £2.4m over 16 weeks. The construction zone was sectioned off behind a temporary full-height jumbo stud partition so the client's business carried on, with civils and steel, three goods lifts, new conveyors with compressed air and fire suppression, and new sprinklers, lighting and detection.

Client
Confidential
Location
Kettering
Value
£2.4 million
Construction
16 weeks
Building
200,000 sq ft
Warehouse floor with column guards and racking beyond
The finished floor, before the racking went in.
Office break space inside the distribution centre
The office break space.

Sealed off

A temporary full-height jumbo stud partition kept the operation dust-free.

No shutdown

A floor inside a floor

35,000 sq ft of mezzanine on new civils and steel framework.

35,000 sq ft

Moving goods

Three goods lifts and new distribution conveyors with compressed air and fire suppression.

3 lifts

Life safety

New sprinklers, high and low-level lighting and fire detection.

16 weeks

Operatives carrying panels on the works side of the partition
Panels going in, on the works side of the partition.
No shutdown. No dust on the pick faces. Every order went out.

Industrial & logistics

Need to build without stopping the operation?

Parogon builds inside working warehouses, plants and distribution centres, behind the partitions that keep your business running.

Talk to Parogon

Your next step

Want a space like this?

Tap through four quick steps and watch your project take shape, or book a 20-minute call with the team.

or call 01483 799433

20+ years NHS & Ministry of Justice partner Scope, cost and programme agreed up front